(Part # 6) Post Brackets,Bolts, and Posts (Part # 7):Determine where you would like your posts to be located on the front gutter assembly. Give us a call and we'll discuss the easiest method to use for your situation. Next, drill two 3/8" holes in the bottom of the gutter to mount the post brackets to the gutter using the slotted head bolts and placing a well caulked fender washer in the interior of the gutter for each hole. Secure the bracket to the gutter with the nuts. Place the gutter in position on the ground to be used as a template for the location of the posts. BE SURE TO TAKE INTO CONSIDERATION THE DISTANCE AWAY FROM THE WALL HANGAR AND THE SLOPE OF THE AWNING. You might want to elevate the end nearest the structure to allow for the slope calculation. This can be done at ground level using the wall your hangar is attached to as a starting point or by using a plumb from the hangar to the ground if the hangar is attached to an eave. After locating the position of the bottom of the posts, mark the spot and fasten the post bracket to concrete with the anchors provided. Set the posts and check the gutter for level. In most cases, one or more posts must be cut to achieve a level gutter assembly. Remember it's real easy to cut the posts down in size, but VERY difficult to make them longer !! In cases of longer awnings where there are 2 or more downspout assemblies, the center of the awning can be slightly elevated in order to facilitate proper drainage to all the downspouts. When you are satisfied with the horizontal level of the front gutter, secure the posts with the nuts and bolts provided. Remember that the self tapping screws are used for the extruded front and side fascia pieces and to attach the pans to them, whereas the sheet metal screws are used to attach rollformed material to rollformed material such as the awning pans to the wall hangar. "Square" up the awning perimeter by temporarily installing an awning pan about every 6 to 10 feet. ! This is IMPORTANT !
(Part # 8) Awning Pan Installation:The pans should be placed as squarely and as deep as possible into the wall hangar channel. Also the other end of the pan should rest approximately 1/4" past the interior lip of the gutter assembly. This 1/4" overhang facilitates proper drainage into the gutter and allows for cleaning of the gutter. With the perimeter installed and squared up, start installing the awning pans on the left side of the awning (left is determined by facing the structure to which the awning is being attached). The edge of the very first and the very last pan ride in the upper slot of the extruded side fascias. You may need to "squeeze" the pans slightly as you go in order to stay on the marks you have placed on the wall hangar and the gutter. The pans are designed to interlock by "rolling" the edge of each consecutive pan into the lock of previously installed pan. Screw down each pan as you go and pay attention to your spacing marks as you progress. Continue installing panels and reuse your "temporary" stabilizing panels as you go. Occasionally check both corners for squareness. If a correction needs to be made, do it immediately, as the awning becomes stronger with each screw that is applied! When all awning pans are securely fastened in place, screw both the far left and the far right pans to the extruded side fascias using self-tapping screws.
(Part # 9) Flashing:Depending on your situation, you may want to caulk your flashing installation both before and after you install the flashing. Install the flashing to the structure by tucking it under the existing roofing material or edge metals if possible and screwing it to the awning ONLY ON THE VERY TOP OF THE INTERLOCKS of the awning pans. This will provide a screw every TWO feet on the top of the awning. Caulk where necessary. Apply caulking over all exposed screw heads on the top of the awning. If you are installing your unit directly underneath an overhang projecting 12" or more from the structure and the unit will be installed within 5 inches of the underside height of the overhang, the flashing is not normally needed. Ask us if you have any questions. Downspout kits:The downspout kit includes a drop elbow (Part # 10), a 10' section of downspout (Part # 11), and an elbow (Part # 12). With a level, determine which way the water will run in the gutter. At the lowest location on your awning gutter, place the drop elbow on the underside of the gutter (as close to a post as possible) and hold the assembly in place while you mark the underside of the gutter for the installation of the drop elbow. Trace the interior hole and screw holes of the drop elbow. Using a hole cutter or a series of drill bit holes, create a drain for the gutter into the center of the flange. Caulk the flange and using self-tapping screws, install the drop elbow on to the gutter. Install the downspout with 2 sheetmetal screws onto the drop elbow. The elbow should slide inside the downspout. Attach the strap and bottom elbow with sheetmetal screws. Corner Pieces:(Part # 14) The corner pieces are installed by pre-drilling them at about a 1" offset (see the diagram) and using self-tapping screws to penetrate the perimeter extrusions and the end caps.
That's all there is to it !
Warranty:The finish on your new awning is protected by a 10 Year Limited Warranty against chipping, flaking or peeling. To keep it fresh looking, give it a rinse with a garden hose every year or so. About every 2 years, you might consider washing it with a mild liquid dishwashing soap and a soft cloth. |
||||||||||||||||||||||||||||||||